Floor no.2

The plan is to get the bathroom floorboards clean and dust free so they can be sealed today (Friday) then left overnight to dry before a coat of oil tomorrow. This is only practical to do at the weekend when the dust monsters are away. Firstly they need a light sand just to smooth any… Continue reading Floor no.2

Clean & tidy!

Yesterday me and Cat had a big clean and tidy. You can get across the dining room floor now the oak has been moved. Everything we need is on the big shelving unit, organised and accessible. We also washed everything as the dust left nothing untouched! We have swept and hoovered the bathroom, landing and… Continue reading Clean & tidy!

Flagstone sealing weekend

We have been putting the flagstone sealing weekend off for a while as we knew it was going to be physically hard, but we have to seal the flagstone floor in the sitting room to protect it after it was cleaned a few weeks ago. We covered the floor up with Ram Board immediately after… Continue reading Flagstone sealing weekend

Ugh day

Cat’s window world of pain continues with paint and putty compatibility issues… We are using water based Farrow & Ball metal primer, but the putty is linseed oil based. In a test on this window the paint is bubbling and not drying because the putty underneath it is not dry (this can take over 2… Continue reading Ugh day

Yet more steel…

Dan is back up in the attic today fixing the steels to the oak purlins ready for Tom to build the purlins back into the gable end wall. These two purlins to the right of the chimney breast are by far the worst ones, neither of them have reached the wall for some time… Bits… Continue reading Yet more steel…